Network Diagram Calculate Early Start Example
Free Printable Network Diagram Calculate Early Start Example
In the process of creation of network diagram several books and reference material talks about various ways to calculate early start es for activity node like some suggest to start es of the first activity with 0 and others suggest it to start with 1.
Network diagram calculate early start example. This tends to create confusion among the students preparing for pmp certification. By doing this the start of the network diagram is the end of day zero. So es for task 5 is 14 days dependent on task 4 which is the longer task. For forward pass calculate the early start es and early finish ef.
Draw a network diagram task 1 4 days task 2 5 days task 3 3 days task 4 7 days task 5 4 days 0 4 4 9 14 18 4 7 147 task 5 is dependent on task 2 and task 4 being complete. Please use the page numbered link below to navigate. We will start from the beginning and proceed to the end. Perform forward pass on critical path.
So with this notations initially with all the placeholders the network diagram looks as follows. In the forward pass the early start and early finish values for each activity along with the overall project duration are calculated. Calculate early start and early finish of activities on critical path. Finally the float is calculated which is an output of the network diagram.
This has been a lengthy lesson let us summarize in the next page. Perform a forward pass to determine the early start es and early finish ef dates. The next step is to calculate early start and early finish of each activity. In order to find out the early start early finish late start and late finish we will use the following activity node description.
Calculating early start es and early finish ef to calculate the early start and early finish dates we use the forward pass. How to calculate critical path. Let us take a simpler example than john s home construction example we saw in previous lessons. In other words critical path is the longest path in your project s schedule network diagram and is the shortest possible duration for the project.
We need to start with activities on critical path. To facilitate schedule calculations an end of day notation is used for both the early start and the late start values. Determine the early start es and early finish ef of activities in a pdm network diagram. The procedure for drawing the network diagram is as follows.
Step 3 1. For the purpose of this example let us assume that activity duration is mentioned in number of days. Let us go back to our example and calculate early late start finish for the entire schedule network diagram. Project schedule network diagram indicating critical path in bold step 3.
Early start finish and late start finish for the entire schedule network diagram. This project involves assembling a train set.